Covid-19 impact on international distribution contracts

Marcello Mantelli
Avvocato in Milan and Turin

As known, the impact of the Covid-19 Pandemic on international contracts began to have its effects on commercial transactions from the first quarter of last year. Since then, companies have had to understand how to resolve issues relating to force majeure, hardship and their impact on ongoing international contracts and those yet to be signed.

After more than a year, these issues are still relevant today. We therefore consider it useful to provide some operational features in the context of our abc on international distribution, in order to correctly manage commercial relations already in progress or to be started.

The cardinal principle of Roman law on the value of contractual agreements lies in the “pacta sunt servanda” rule (the agreements must be respected), incorporated into Italian law with the provision contained in art. 1372 of the Civil Code according to which the contract has the force of law between the parties and, for example, in English law with the principle of the so-called sanctity of contract.

In other words, the rights and obligations governed by the parties at the time of completion of the contract are and remain binding even in the event that during their execution there is a change in circumstances with respect to those existing at the time of the signing that does not allow the exact execution.

However, the rule bears exceptions in the sense that under certain conditions the party affected by an unforeseeable event at the time of the stipulation can invoke a legal or contractual excuse to be exempt from liability arising from its non-performance.

A sadly known example is that of the Pandemic and the related emergency legislation which prevented the execution of numerous contracts for at least a certain period of time. On the other hand, the hypothesis constituted by an unforeseen event that can be overcome by the affected party, bearing a higher cost, is different. Here it is not impossible to fulfill but it is much more expensive (so-called hardship).

In such cases, if there is an impediment to the execution of a contractual obligation that the party is unable to overcome, or if the execution requires an excessively heavy economic burden, the party can therefore be temporarily or permanently “released” from contractual obligation but only under certain conditions. Let’s see which ones.

Facing a situation of force majeure and in the specific case in which the contract between the parties is synthetic and does not include either a clause on the applicable law or a clause on force majeure, it will be necessary to verify which law is applicable to the contract by virtue of the rules of private international law.

To avoid margins of uncertainty, the most practical and understandable solution for companies is therefore to provide, within the international contract, specific force majeure/hardship clauses in order to be able to have, already in the contract, solutions that make it possible to flexibly deal with any situations of “crisis” of the services deriving from the aforementioned circumstances that occurred after the stipulation.

It is also essential that the force majeure/hardship clauses considered define which types of circumstances are considered “impediments to performance” and which types of effects unfold on the original obligations of the parties (renegotiation, withdrawal, determination by a third party, etc.).

Therefore, a contract is always binding even in the event that there is a change in circumstances, but in the event of an unforeseeable impediment it is necessary to assess on a case-by-case basis whether the conditions exist to be temporarily – or definitively – relieved of one’s contractual commitments in derogation from the pacta sunt servanda principle.

In particular, if events occur that make the performance impossible or excessively burdensome, it is possible to invoke such events as force majeure/hardship that prevent the execution on the basis of the contract or, failing that, of the applicable law (or on the basis of both in the case of a “laconic” clause).

Therefore, to ensure that the contract can be adapted to changed circumstances, it is always necessary to provide from the time of stipulation specific clauses that allow a margin of flexibility and adaptation to new circumstances in order to safeguard, as far as reasonably possible, the economic operation.

If this has not been done in due time or if it has been done in an inappropriate way with inappropriate clauses, it is strongly advisable to renegotiate the contracts in progress so as to do business safely and to avoid disputes between the parties.

#abcdistribution #internationaldistribution #abcinternationaldistribution #internationalcontracts #tradelaw #coronavirus #hardship #forcemajeure #covid19 #internationalcontractsforcemajeure #internationaldispute #internationallitigation

Condividi su:

Leave a Reply

Your email address will not be published. Required fields are marked *

*